Live Tests are always done for Controls in single and three phase particular to the panel under Test. Live Load Tests can be carried in agreement for Client for large number ATS modules and Dual KWHM for Export.

Testing the Panels for Quality and Functionality is a very important Task for the uniformity of installations at the Clients Site.

Copyright Engineering & Contracting Services Co. All rights reserved. 

Dead, Visual, Creepage, Voltage, current and leakage tests are carried on all Panels:

Testing the Panels

  • Test of dielectric properties, clause 8.2.2 of IEC 60439-1
  • Test of the short-circuit withstand strength, clause 8.2.3 of IEC60439-1
  • Verification of the effectiveness of the protective circuit, clause 8.2.4of IEC 60439-1
  •  Check for clearances and creepage distances, clause 8.2.5 of IEC 60439-1
  • Mechanical operation, clause 8.2.6 of IEC 60439-1
  • Verification of the degree of protection, clause 8.2.7 of IEC 60439-1
  • Verification of the resistance of insulationmaterials to abnormal heat and fire (glow-wiretest), clause 8.2.9 of IEC 60439-1.
  • The vertical and horizontal Bus Bars arecompartmented. They should be fully segregated as per the required Form to IEC 60439-1. the inner segregation plates as well as the functional units. They should be in accordance with the required Form to IEC 60439-1.